Scanclimber’s innovative solution for chimney demolition

Published 2/4 at 13:20

A demolition project in Berlin presented a unique and demanding challenge in the dismantling of three 80m high chimneys located atop a 100m tall structure. Traditional methods of deconstruction proved impractical due to the absence of cranes and the complexities of transporting workers and equipment to such heights. Scanclimber’s ‘Mast Climbing Work Platforms’ (MCWPs) delivered an effective and innovative solution to overcome these obstacles.

The solution

Scanclimber supplied a tailored combination of mast climbers to meet the project’s unique requirements comprising of its Twin SC8000. This consists of a twin custom configured square mast climbing work platform used to transport personnel, tools, and materials to the required heights safely and efficiently. The twin square mast climber configuration was designed to operate from +98m to +178m, providing stability and versatility for tasks at extreme heights. The ability to dismantle the mast sections independently further optimised the timeline and reduced reliance on additional equipment.

The deployment of Scanclimber’s MCWPs resulted in numerous benefits. They provided seamless access to all work areas, significantly simplifying the dismantling process and created a secure environment for workers, eliminating risks associated with crane based methods. The use of the platforms facilitated the transport of personnel and tools directly to the work site, saving time and effort. Workers were also able to conveniently connect power tools directly to the platform power sockets, reducing downtime and eliminating the need for long extension cables from the ground. The easy installation and dismantling of mast sections reduced overall project time and minimised operational costs.

 

Overcoming challenges

The initial project concept involved using cranes to secure and remove dismantled sections. However, Scanclimber’s innovative approach with a custom configured twin square platform eliminated the need for cranes altogether, streamlining operations while maintaining safety and precision. Scanclimber’s adaptability ensured the project remained on track, with the platforms’ reliability and robust design proving essential in navigating the complexities of the task.

The dismantling of the chimneys progressed successfully, with an expected completion in 2025. Scanclimber’s MCWPs are said to have not only enhanced efficiency and safety but also demonstrated the versatility required for highly specialised projects. As projects continue to push the boundaries of engineering, Scanclimber states that its innovative solutions remain indispensable in turning challenges into achievements.

www.scanclimber.com

Join our Newsletter

PDi TV

Info

×